The Centre gave Stage-I in-principle approval for the use of 190.7 hectares of forest land for a proposed 1,300 MW pumped storage hydropower project in West Karbi Anglong, subject to environmental safeguards.
Assam Power Distribution Company Limited (APDCL) proposed the project, which is planned in the Hamren Forest Division. It will be an off-stream, closed-loop pumped storage hydropower project and will require an extensive power transmission network.
The advisory committee of the Union Ministry of Environment, Forest and Climate Change considered APDCL's proposal at a meeting in New Delhi and recommended first-stage approval subject to conditions.
The land includes 3.27 hectares of very dense forest, 94.07 hectares of moderately dense forest and 64.41 hectares of open forest. The project will require the felling of around 3,940 trees of 50 species and 2,66,300 bamboo culms.
The committee said the project would strengthen the integration of power generation with renewable energy systems, reduce dependence on conventional energy sources and could contribute to the region's socio-economic development.
The state government must prepare a site-specific wildlife management plan in consultation with the Chief Wildlife Warden. The plan must include measures to protect wildlife and habitats in the forest area.
It must also prepare and obtain approval for a Catchment Area Treatment Plan and a Soil and Moisture Conservation Plan to prevent erosion. APDCL will bear the cost of implementing these plans.
The project must draw water to fill its reservoir for the first time only during the monsoon, when river flows are at their peak. It must also undertake rainwater harvesting, groundwater recharge and water conservation measures, besides complying with approved dam designs and applicable safety standards.
Construction debris disposal sites must be restored after the work is completed.